Back to Top

Solar Projects


STATUS OF DIFFERENT SOLAR PROJECTS OF WBSEDCL AS ON 17.11.2018

Sl. No. Type of Project Name of the Project Present Status Remarks
1 Roof Top Grid Connected Solar PV Power Plant 100 Schools Grid-connected Solar Roof top Programme of WBREDA Project Completed. 92 nos. of already installed and running successfully. Later WBREDA took up the work and rest of the schools had been completed by them Total Cumulative Generation as on 31.10.2018 is about 4.00 MU.
2 200 Schools Grid-connected Solar Roof top Programme of WBSEDCL Plants already commissioned - 140 140 nos. of school installation work completed as per fund sanctioned by the State Government.
3 5.125 MW Rooftop Solar PV Plant (5 kWp each) Project under IPDS Programme LOA has been placed for all 19 no of packages and work is under progress. 400 KW installed & commissioned as on 31.10.2018. Target date of completion: December 2018.
4 10.5 MW Rooftop Solar PV Plant (Min. 10 kWp each) Project under Alo Shree Programme LOA has been placed for all 5 nos. of packages and work is under progress. 600 KW installed & commissioned as on 31.10.2018.Target date of completion : December 2018
5 Ground Mounted Grid Connected Solar PV Power Plant Teesta Canal Bank Solar PV Power Project (10 MW) Project Completed. Project commissioned on 18.08.2016 and now running in full capacity.
Total Cumulative Generation as on 31.10.2018 is about 29.74 MU.
6 10 MW Solar PV Project at Mejia, Bankura Project Completed 10 MW commissioned on 15/12/2017 and now running in full capacity.
Total Cumulative Generation as on 31.10.2018 is about 6.3893 MU.
7 10 MW Solar PV Project at Charrah, Purulia Project Completed 09 MW commissioned as on 30th April 2018.
Total Cumulative Generation as on 31.10.2018 is about 5.8200 MU.
8 10 MW Solar PV Project at Santaldih, Purulia Work is under progress. Expected to be commissioned: December 2018
9 10 MW Solar PV Project at Khemasuli (Patni), Paschim Medinipur. Work is under progress. Expected to be commissioned: November 2018
10 10 MW Solar PV Project at Salboni, Paschim Medinipur Work is under progress. Expected to be commissioned: December 2018
11 06 MW Solar PV Power Project at Atna Execution Order has been placed and project work is under progress. Expected to be commissioned: June 2019.
12 10 MW Solar PV Power Plant at Kadlagora, Manbazar Block - I of Purulia district Execution Order has been placed and project work is under progress. Expected to be commissioned: June 2019.
13 10 MW Solar PV Project at Chalbalpur Raniganj, Burdwan district. Execution Order has been placed and project work is under progress. Expected to be commissioned: June, 2019
14 10 MW Solar PV Project at Koltaldih (Phase - I), Asansol, Burdwan district Execution Order has been placed and project work is under progress. Expected to be commissioned: July, 2019
15 Canal Top Solar PV Power Project 10 MW Solar PV power plants on canal top of TCFHP Tail Race Canal, Stage II Power Station at Haptiagachh in Uttar Dinajpur District. Work is under progress. Expected to be commissioned: March, 2019
16 10 MW Solar PV Power Plants at Mahananda Main Canal Haptiagachh, Uttar Dinajpur DPR has been submitted to the Power & NES Dept. GoWB for sanction under RIDF scheme XXIII of NABARD. Approval is awaited from Dept. Of Power, NES, Govt. Of West Bengal
17 Ground Mounted Grid Connected Solar PV Power Plant 10 MW Solar PV Power Plant at Ichamara at Purulia District DPR has been submitted to the Power & NES Dept. GoWB for sanction under RIDF scheme XXIV of NABARD. Approval is awaited from Dept. Of Power, NES, Govt. Of West Bengal
18 10 MW Solar PV Power Plant at Kalpani-Baldiahati at Coochbehar District DPR has been submitted to the Power & NES Dept. GoWB for sanction under RIDF scheme XXIV of NABARD. Approval is awaited from Dept. Of Power, NES, Govt. Of West Bengal
19 03 MW Solar PV Project at Leusipukuri, Darjeeling district Technical Commercial Bid opened on 16.11.2018. Techno Commercial evaluation is under process.
20 10 MW Solar PV Project at Andherijhari, Uttar Dinajpur district Financial Bid opened on 16.11.2018. LOA will be placed on December 2018.
21 10 MW Solar PV Project at Srirampur, Jhargram, Paschim Medinipur district
22 10 MW Solar PV Project at Koltaldih (Phase - II), Asansol, Burdwan district
23 10 MW Solar PV Project at Dhaka - I at Birbhum district, West Bengal
24 10 MW Solar PV Project at Dhaka - II at Birbhum district, West Bengal
25 Solar Park (Ground Mounted Grid Connected Solar PV Power Plant) 200 MW Solar Park, at Dadanpatra, Purba Medinipur Revised Detailed Project Report of 200 MW Solar Park, at Dadanpatra, Purba Medinipur has been prepared and submitted on 28/04/2017, as advised by Power Department. The Project is awaiting approval of MNRE, GOI towards taking up the execution work. CRZ clearance would be required as per recent MNRE observation on the DPR submitted by WBSEDCL. Accordingly Digitized map of the proposed Solar Park along with EIA & EMP report has been submitted to WBCZMA (West Bengal Coastal Zone Management Authority) on 14.08.2018 for CRZ clearance and reports will be available by November 2018.


Land availability Report for Solar PV Power Projects

1. Land has been identified for Solar PV Power Project at Mouza Basadhara Natrihari, Block - Coochbihar - II and Site visited on 25.07.2018 and found suitable for solar project and found suitable for 70 MW Solar Park Project.

Block Mouza JL. No. Plot No. Kh. No. Classification Area(in Acre) Remarks
Coochbihar - II Basadhara Natrihari 02 1670     67.79 Vested land
Coochbihar - II Basadhara Natrihari 02 301     216.95 Vested land
Total
284.74  




2. Land (Appx 5 acres) has been identified for Solar PV Power Project at Mouza - Barail, J.L. No. 225 under Block Bansihari at Dakshin Dinajpur District and will be visited soon.


WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED

Solar Power Generation department

Scheme-wise Expenditure Report of Solar PV Power Projects on State Development Scheme up to 17.11.2018

Sl. No. Name of Projects Name of the Scheme Implementing Agency Approved Total Outlay Awarded Cost Funding Agency Fund released up to 31/03/2018 Expediture up to 31/03/2018 Fund released during 2018-19 Expediture during 2018-19 Cumulative Fund released Cumulative Expenditure Remarks
    SOLAR PROGRAMME   (Rs. in Crore) (Rs. in Crore)   (Rs. in Crore) (Rs. in Crore) (Rs. in Crore) (Rs. in Crore) (Rs. in Crore) (Rs. in Crore)  
1 2 3 4       4 5 7 8 9(4+7) 10(5+8) 12
Major Head of A/c : 4801-SP(RIDF)
1 10 MW Teesta Canal Bank Solar PV Project at Haptiagachh, Uttar Dinajpur RIDF : XXI Ujaas Energy Limited 66.3699 65.88 + Service Tax NABARD and State Govt. 51.3699 64.0687 0.0000 0.3284 51.3699 64.3971 Plant Commissioned on 18.08.2016
2 10 MW Solar PV Project at Mejia, Bankura RIDF : XXI BHEL 61.3400 56.0623 + Service Tax NABARD and State Govt. 56.0623 32.7399 1.6942 1.7311 57.7565 34.4710 Project commissioned on 15.12 2017
3 10 MW Solar PV Project at Santaldih, Purulia RIDF : XXI BHEL 61.9400 56.6090 + Service Tax NABARD and State Govt. 56.6090 18.0017 2.6026 3.5199 59.2116 21.5216 Target Commission : Dec, 2018
4 10 MW Solar PV Project at Chharrah, Purulia RIDF : XXI BHEL 61.2400 56.0623 + Service Tax NABARD and State Govt. 56.0602 27.5688 0.3768 5.1055 56.4370 32.6743 9 MW Commissioned in April, 2018
5 10 MW Solar PV Project at Patni (Khemasuli), Paschim Medinipur RIDF : XXII Vikram Solar Limited 60.1786 44.7280 + service Tax NABARD and State Govt. 31.4434 0.0000 13.2848 18.6432 44.7282 18.6432 Target Commission : Nov. 2018
6 10 MW Solar PV Project at Salboni, Paschim Medinipur RIDF : XXII Vikram Solar Limited 60.0066 44.6280 + service Tax NABARD and State Govt. 28.5620 0.0000 11.6030 15.9409 40.1650 15.9409 Target Commission : Dec. 2018
7 6 MW Solar PV Project at Atna, Purulia RIDF : XXII Exide Industries Limited 35.8400 26.6444 + GST NABARD and State Govt. 0.0000 0.0000 5.3289 0.0000 5.3289 0.0000 Target Commission : June, 2019
8 10 MW Canal Top Solar PV Project at TRC of TCF Stage-II, Haptiagachha, Uttar Dinajpur RIDF : XXII PES Engineers Pvt. Ltd. 61.8457 84.4908 + GST NABARD and State Govt. 25.0347 0.0000 0.0000 6.4046 25.0347 6.4046 Target Commission : March, 2019
9 10 MW Solar PV Project at Kadlagora, Manbazar Block - I, Purulia RIDF : XXII Vikram Solar Limited 60.1032 41.8100 + GST NABARD and State Govt. 0.0000 0.0000 8.3620 3.2490 8.3620 3.2490 Target Commission : June, 2019
10 10 MW Solar PV Project at Andherijhari, Uttar Dinajpur RIDF : XXIII   51.0425   NABARD and State Govt. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 LOA will be placed on Decmber 2018
11 03 MW Solar PV Project atLeusipukuri, Darjeeling RIDF : XXIII   20.4714   NABARD and State Govt. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 LOA will be placed on Jan 2019
12 10 MW Solar PV Project at Srirampur, Jhargram RIDF : XXIV   51.5600   NABARD and State Govt. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 LOA will be placed on Decmber 2018
13 10 MW Solar PV Project at Chalbalpur, Raniganj, W. Bardwan RIDF : XXIV Vikram Solar Limited 52.8700 41.94 + GST NABARD and State Govt. 0.0000 0.0000 8.3880 3.2490 8.3880 3.2490 Target Commission : June, 2019
14 10 MW Solar PV Project at Koltaldih (Ph - I), Asansol, Paschim Bardhaman RIDF : XXIV Vikram Solar Limited 51.5200 41.72 + GST NABARD and State Govt. 0.0000 0.0000 8.3440 3.2490 8.3440 3.2490 Target Commission : June, 2019
15 10 MW Solar PV Project at Koltaldih (Ph - II), Asansol, Paschim Bardhaman RIDF : XXIV   51.5200   NABARD and State Govt. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 LOA will be placed on Decmber 2018
16 10 MW Solar PV Project at Dhaka-I, Birbhum RIDF : XXIV   51.0500   NABARD and State Govt. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 LOA will be placed on Decmber 2018
17 10 MW Solar PV Project at Dhaka-II, Birbhum RIDF : XXIV   51.0500   NABARD and State Govt. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 LOA will be placed on Decmber 2018
 
TOTAL RIDF
    909.9479     305.1415 142.3791 59.9843 61.4206 365.1258 203.7997  
Major Head of A/c : 4801-SP(WBETF)
1 10 MW Canal Top Solar PV Project at TRC of TCF Stage-II, Haptiagachha, Uttar Dinajpur STATE PROGRAMME PES Engineers Pvt. Ltd. 26.5054   NABARD and State Govt. 5.3010 0.0000 0.0000 0.0000 5.3010 0.0000 Target Commission : March, 2019
 
TOTAL WBETF
    26.5054     5.3010 0.0000 0.0000 0.0000 5.3010 0.0000  
  ROOFTOP SOLAR PV PROJECTS
  1 MW Solar PV Rooftop Project for 100 nos. School (WBSEDCL executing 92 Schools)   M/s Sunshine, M/s Suncraft, M/s Pulse Power 9.19 9.19 State Govt. 7.67925 0 0 0 0 8.6171 RTSPV Plant commissioned in 92 schools within 31.03.2016.
  2 MW Solar PV RoofTop Project for 200 School (WBSEDCL executing 140 schools)   Vikram Solar Limited 15.658 13.82 State Govt. 10.9606 0 0 0 0 5.8918 140 nos. school completed
  10.5 MW Rooftop Solar PV Project For WBSEDCL/WBSETCL/ other Govt. Buildings   M/s Lase Power Infra Pvt. Ltd.
M/s Vikram Solar Ltd., M/s TATA Power, M/s L&T
74.0058 60.29244 State Govt. 0 0 0 0 0 0 Work is in progress. 600 KW commissioned as on 31.10.2018
  Total     98.8538 83.30244 0 18.63985 0 0 0 0 14.5089