Back to Top

INTEGRATED POWER DEVELOPMENT SCHEME (IPDS)


Background

The MoP, GOI has launched Integrated Power Development Scheme (IPDS) for strengthening of Distribution Infrastructure for the Urban areas having population of more than 5,0000 as per census 2011 with the following components:

➢ Strengthening of sub-transmission & distribution networks including provisioning of Solar Panels and Net-metering.

➢ Metering of distribution transformers / feeders / consumers.

➢ IT enablement of distribution sector and strengthening of distribution network.


Broad Objective of the Scheme

➢ 24x7 Power supplies for consumers.

➢ Reduction of AT&C losses as per trajectory finalized by MoP in consultation with States

➢ Providing access to power to all households


Nodal Agency

Power Finance Corporation (PFC) was the Nodal Agency for operationalization and implementation of the scheme under the overall guidance of MoP.


Project Management Agency (PMA)

As per the guideline for IPDS two Project Management Agency (PMA) had to be appointed utility-wise to ensure timely implementation of the project. Accordingly RECPDCL and PFCCL have been appointed by WBSEDCL for IPDS.


Mode of Implementation

The projects were executed on turn-key/ partial turn-key/ departmental basis, through e-tendering.


Implementation Period

Projects under the scheme were completed within a period of 24 months from the date of issue of Letter of Award (LOA) by the utility.


Monitoring Committee

Monitoring Committee, constituted by MoP, GOI is approving authority of all schemes.


Financial support Mechanism for IPDS in WBSEDCL


Agency Nature of Support Quantum of support
(Percentage of Project Cost)
Govt. of India Grant 60%
Govt. of West Bengal Grant 25%
WBSEDCL Contribution Own Fund/Loan 15%
Additional Grant from GOI on achievement of prescribed mile stones Grant 50% of Total loan component


Scope of work and Status as on 31.03.2022


Scope of work Quantity Sanctioned Project cost (Rs. in Cr.) Complete as on 31.03.2022 Status as on 31.03.2022
New 33/11 kV sub-station with associated 33 kV line. 50 Nos. (2x10 MVA) 402.64 50 Nos. 50 Nos. sub stations have been successfully commissioned.
33 kV system augmentations with renovation of existing 33/11 kV sub-station (No. of PTR) 167 Nos. 392.53 167 nos. Completed at 167 Nos. substations.
Drawal of 11 kV line (New & augmentation). 1576 KM 376 1357 KM Work Completed
Drawal of LT line (New & augmentation). 278 KM 145.72 128 KM
Drawal of AB Cable. 15,373 KM 1,082.58 14641 KM
Installation of DTR. (New & augmentation). 8,137 Nos 230.69 7739 Nos.
Replacement of Meter. 7,86,452 Nos 220.93 7,31,661 Nos.
Installation of Roof top Solar panel. 4335 Kwp 38.28 4160 Kwp Work completed
New 33/11 kV sub-station with associated 33 kV line under IPDS GIS. 10 Nos 87 8 Nos Work Completed for 8 Nos SS
Implementation of lT infrastructure in 50 IPDS towns under IPDS Phase-II, IT Project. (DC/DRC upgradation /GIS/ MDAS) 50 Towns 31.51 Successfully completed Successfully Completed.


Status of fund and expenditure(incl. IPDS GIS & IPDS IT)


Status of fund and expenditure as on 31.03.2022
Fund received from MOP, GOI Rs. 1669.18 Crore
Fund received by GOWB Rs. 703.24 Crore
Fund received through REC Loan Rs. 434.39 Crore
Fund utilized (incl. PMA charges) Rs. 2801.80 Crore