Background

Govt. of India, vide Office Memorandum F.No.44/44/2014-RE dated 3rd December 2014 issued by the Ministry of Power, launched Deendayal Upadhyaya Gram Yyoti Yojana (DDUGJY) with the following components

  1. Separation of agriculture and non-agriculture feeders for supply to agricultural & non-agricultural consumers in the rural areas for effective demand side management.
  2. Strengthening and augmentation of sub-transmission & distribution (ST&D) infrastructure in rural areas, including metering at distribution transformers, feeders and consumer end.
  3. Rural electrification, as per CCEA approval dated 01.08.2013 for completion of the targets laid down under RGGVY for 12th and 13th plans.

Board Objective of the Scheme

     Providing access to power for all households.

     24X7 Power

     AT&C loss reduction as per trajectory finalized by MoP.

Scope of Works specific to achivements of the broad objectives:

Access to Power for all households :

Electrifiction of un electrified(UE) villages and creation of new village infrastructures for access to power for all house holds


24X7 power supply for non-Agri-consumer and adequate supply for Agri-consumer :

Physical seperation of HT feeders for Agricultural and non-Agricultural consumers.


AT&C loss reduction :

Strengthening of sub-transmission & distribution sysytem and metering at all levels of distribution network.


Sailent Features of the Scheme :

Nodal Agency :    Rural Electrification Corporaion Limited(REC) is the Nodal Agency operationalisation and implementation of the scheme under the overall guidance of MoP.

Project Management Agency (PMA) :    REC Power Distribution Company Ltd(RECPDCL)and PFC Consulting Ltd(PFCCL) have been appointed as Project Management Agency(PMA)to assist in project management as well as timely implementation of the project.

Mode of Implementation :    The projects shall be implemented on turn-key basis.However some work will be executed on partial turnkey/departmental basis for which approval has been received from the Monitoring Commitee,MoP,GOI.

Implementation Period :    Projects under the scheme shall be completed within a period of 24 months from the date of issue of Letter of Award (LoA). For execution of work on partial turnkey/departmental basis, project needs to be completed within 30 months from date of communication of the approval of the Monitoring committee.

Funding pattern of the Scheme :


Agency Nature of Support Quantum of support
(Percentage of Project Cost)
Govt.of India Grant 60%
State Contribution Grant 25%
WBSEDCL own Contribution/Loan Own
contribution/Loan
15%


Approval of the Project by Nodal Agency:
The component wise cost as per district wise submitted DPRs were approved in the 6th Monitoring commitee held on 10/12/2015 and comminucated by the Nodal Agency The REC Ltd.vide memo no:REC/ZO/KOL/DDUGJY/2015-16/834 Dated 01/02/2016

Component wise Sanctioned cost :


Sl.No Items Cost
(Rs in Crore)
1 Electrification of Un electrified villages. 46.86
2 Sansad Adarsh Gram Yojana (SAGY) 0.60
3 Metering 441.22
4 Feeder Separation 1159.96
5 Access to rural Households 1729.93
6 System Strengthening 862.34
  Total Project Cost: 4240.90
7 PMA Charges @0.5% of total project cost 21.20
  Total Sanctioned project cost 4262.10
8 PMA Charges @1% of total Project cost (Borne by WBSEDCL) 42.40
  Total Project Cost : 4304.50


DPR wise sanctioned cost Under the Project

SlNo. Name of District Elect of UE Villages SAGY Metering Access to rural HH System Strength enling Feeder Separation Total Financial Involvement
(Rs.in Crores)
1 Bankura Nil Nil 19.99 102.03 35.77 68.12 225.91
2 Bardhaman Nil Nil 28.47 141.43 75.17 145.63 390.7
3 Birbhum Nil Nil 26.55 96.31 46.58 117.45 286.89
4 Dakshin
Dinajpur
Nil Nil 14.07 58.27 33.53 34.88 140.75
5 Darjeeling Nil 0.6 8.72 47.63 45.23 9.82 112
6 Howrah Nil Nil 24.65 46.3 45.41 5.24 121.6
7 Hoghly Nil Nil 20.52 148.43 24.89 72.9 266.74
8 Jalpaiguri Nil Nil 9.99 55.1 53.71 16.28 135.08
9 Coochbehar Nil Nil 11.62 41.85 45.75 3.72 102.94
10 Malda Nil Nil 36.51 50.72 81.44 92.37 261.04
11 Mursidabad Nil Nil 26.19 103.84 46.12 117.9 294.05
12 Nadia Nil Nil 24.57 105.47 49.81 88.2 268.05
13 North 24
Parganas
Nil Nil 39.01 152.11 46.82 67.65 305.58
14 North 24
Parganas(Bidhannagar)
Nil Nil 6.03 11.89 2.3 4.15 24.36
15 Paschim
Midnapore
Nil Nil 44.77 175.71 62.47 180.99 463.94
16 Purba
Midnapore
Nil Nil 37.14 99.01 58.12 55.51 249.78
17 Purulia Nil Nil 15.08 67.39 15.05 7 104.51
18 South 24
Parganas
46.86 Nil 33.18 170.26 50.71 43.51 344.51
19 Uttar
Dinajpur
Nil Nil 14.16 56.19 43.47 28.66 142.47
  Total 46.86 0.6 441.22 1729.93 862.34 1159.96 4240.90


DETAIL SCOPE OF WORK UNDER DEENDAYAL UPADHYAYA GRAM JYOTI YOJANA (DDUGJY)


Sl No DETAIL SCOPE OF WORK UNIT QUANTITY FInancial Involvement
(Rs in lakhs)
I ELECTRIFICATION OF UE VILLAGES
(14 no villages in Gosaba,Namkhana & Patharpratima Block under south 24 Pargana District)
     
a) Installation of new DTR No 294 46.86
b) Drawal of new 11KV Spur Line DTR KM 165
c) Drawal of new LT AB Cable KM 530
d) Connection to BPL House Holds No 6,790
         
II FEEDER SEPARATION :
(Physical Separation of HT Feeders for Agricultural & Non Agricultural Consumers)
     
a) New 11KV Bay NO 461 875.76
b) New 11KV Line (621 no feeder) KM 12464
c) Installation of new DTR NO 8573
         
III ACCESS TO RURAL HOUSEHOLDS
(for connecting unconnected households)
     
a) Capacity Augmentation of existing DTR No 3457 1712.87
b) Conversion of existing LT O.H. Line to AB Cable KM 28287.149
c) Installation of new DTR NO 10354
d) New 11KV Spur Line KM 2268.198
e) New LT AB Cable line KM 1328.95
f) New LT O.H Line KM 1084.709
g) Connection of BPL HHs NO 24515
         
(IV) METERING      
a) Installation of Dist Transformer metering NO 27718 319.93
b) Installation of FEEDER Metering NO 512
c) Replacement of defective /electro magnetic(old)consumer Metering NO 1896241
d) Shifting of existing consumer metering NO 414045
         
(V) SANSAD ADARSH GRAM YAJONA      
a) Installation of new 11 KV Bay NO 1 0.51
b) Drawal of new 11KV Line KM 4.2
       
(VI) SYSTEM STRENGTHENING      
a) Drawal of new New 33KV Line KM 1625.2 748.74
b) Augmentation of existing 33 KV Line KM 82
c) Construction of New 33/11KV Sub Station NO 80
d) Augmentation of existing 33/11KV Sub Stations NO 106
e) Drawal of New 11KV Line KM 991
f) Augmentation/Renovation of existing 11KV Line KM 1,926
g) Installation of new 33KV Bay NO 77
         
  GRAND TOTAL:     3704.67




UP-TO-DATE STATUS OF DDUGJY SCHEME AS ON 31.01.2021

A . Status of Work Village Infrastructure for access to power for all Rural Household ,Feeder Separation and Metering work in Turnkey Mode as on 31.01.2021

SL NO: District Item of Work Status of Award/Tender Name of Awarded Turnkey Agencies Staus of work Target for completion
1 North 24 parganas Feeder Segregation LOA Issued M/S L&T Ltd 28 no Feeders are commissioned out of 33 no. feeders. March,2021
Metering 1,97,568 no. defective consumer meters replaced out of 1,97,805 no. in scope.
Village Infrastructure for access to power for all Rural HH. 3,067 km renovation of LT line by AB Cable completed out of 3,072 km in scope.
1,515 no New Distribution Transformer installed out of 1,517 no. in scope.
2 South 24 parganas and Biddhannagar Feeder Segregation LOA issued M/S IL&FS ECC Ltd 07 no Feeders are commissioned out of 10 no. feeders. March,2021
Metering 2,08,400 no. defective consumer meters replaced out of 2,56,990 no. in scope.
Village Infrastructure for access to power for all Rural HH. 2,107 km renovation of LT line by AB Cable completed out of 2,146 km in scope.
672 no New Distribution Transformer installed out of 826 no. in scope. 369 no. augmentation of DTR completed out of 369 no. in scope.
Electrification of 14 UE & 59 PE villages in Sundarban area. LOA issued M/S Sterling & Wilson Ltd Work Completed --
3 Howrah Feeder Segregation LOA Issued M/S Sterling and Wilson Pvt. Ltd 01 no Feeders is commissioned out of 02 no. feeders. March,2021
Metering 1,99,452 no. defective consumer meters replaced out of 2,33,707 no. in scope.
Village Infrastructure for access to power for all Rural HH. 636 km renovation of LT line by AB Cable completed out of 710 km in scope.
223 no New Distribution Transformer installed out of 298 no. in scope.
4 Burdwan Feeder Segregation LOA issued M/S Lumino Ind. Ltd 81 no Feeders are commissioned out of 92 no. feeders.
1,221 no New Distribution Transformer installed out of 1,466 no. in scope.
March, 2021
Metering LOA issued M/S NCC Ltd 1,34,695 no. defective consumer meters replaced out of 1,50,000 no. in scope.
Village Infrastructure for access to power for all Rural HH. LOA issued 3,654 km renovation of LT line by AB Cable completed out of 3,654 km in scope.
955 no New Distribution Transformer installed out of 955 no. in scope.
5 Hooghly Feeder Segregation LOA issued M/S L&T Ltd 27 no Feeders are commissioned out of 31 no. feeders. March,2021
Metering 1,33,762 no. defective consumer meters replaced out of 1,53,762 no. in scope.
Village Infrastructure for access to power for all Rural HH. 2,581 km renovation of LT line by AB Cable completed out of 2,581 km in scope.
1,064 no New Distribution Transformer installed out of 1,306 no. in scope.
6 Birbhum Feeder Segregation LOI Issued M/S L&T Ltd 36 no Feeders are commissioned out of 58 no. feeders. March,2021
Metering 1,12,776 no. defective consumer meters replaced out of 1,14,999 no. in scope.
Village Infrastructure for access to power for all Rural HH. 3,466 km renovation of LT line by AB Cable completed out of 3,469 km in scope.
1,029 no New Distribution Transformer installed out of 1,239 no. in scope.
7 Malda Feeder Segregation LOI issued M/S Bajaj Electricals Ltd. 16 no Feeders are commissioned out of 26 no. feeders. March,2021
Metering 1,00,017 no. defective consumer meters replaced out of 1,00,414 no. in scope.
Village Infrastructure for access to power for all Rural HH. 879 km renovation of LT line by AB Cable completed out of 912 km in scope.
1,504 no New Distribution Transformer installed out of 1,662 no. in scope. 404 no. augmentation of DTR completed out of 404 no. in scope.
8 Murshidabad Feeder Segregation LOA issued M/S SPML Ltd. 39 no Feeders are commissioned out of 50 no. feeders.
266 no New Distribution Transformer installed out of 537 no. in scope.
March,2021
Metering LOA issued M/S L&T Ltd. 1,34,926 no. defective consumer meters replaced out of 1,44,926 no. in scope.
Village Infrastructure for access to power for all Rural HH. 3,313 km renovation of LT line by AB Cable completed out of 3,342 km in scope.
336 no New Distribution Transformer installed out of 339 no. in scope. 712 no. augmentation of DTR completed out of 713 no. in scope.
9 Nadia Feeder Segregation LOA issued M/S L&T Ltd. 33 no Feeders are commissioned out of 33 no. feeders. March,2021
Metering 1,94,975 no. defective consumer meters replaced out of 2,04,975 no. in scope.
Village Infrastructure for access to power for all Rural HH. 3,067 km renovation of LT line by AB Cable completed out of 3,074 km in scope.
1,053 no New Distribution Transformer installed out of 1,129 no. in scope. 243 no. augmentation of DTR completed out of 243 no. in scope.
10 Paschim Midnapur Feeder Segregation LOI Issued M/S ILFS ECC Ltd. 42 no Feeders are commissioned out of 68 no. feeders.
515 no New Distribution Transformer installed out of 1,097 no. in scope.
March,2021
Metering LOA issued M/S L&T Ltd. 1,99,127 no. defective consumer meters replaced out of 2,00,060 no. in scope. March,2021
Village Infrastructure for access to power for all Rural HH. 3,883 km renovation of LT line by AB Cable completed out of 3,890 km in scope.
796 no New Distribution Transformer installed out of 807 no. in scope. 1,435 no. augmentation of DTR completed out of 1,438 no. in scope.
11 Purba Midnapur Feeder Segregation LOA issued M/S L&T Ltd. 06 no Feeders are commissioned out of 10 no. feeders. March,2021
Metering 1,89,056 no. defective consumer meters replaced out of 1,89,100 no. in scope.
Village Infrastructure for access to power for all Rural HH. 2,447 km renovation of LT line by AB Cable completed out of 2,447 km in scope.
1,569 no New Distribution Transformer installed out of 1,633 no. in scope.
12 Bankura Feeder Segregation LOA Issued M/S L&T Ltd. 05 no Feeders are commissioned out of 24 no. feeders. March,2021
Metering 98,661 no. defective consumer meters replaced out of 1,04,510 no. in scope.
Village Infrastructure for access to power for all Rural HH. 1,594 km renovation of LT line by AB Cable completed out of 1,654 km in scope.
769 no New Distribution Transformer installed out of 1,326 no. in scope.
13 Purulia Metering LOA Issued M/S Montecarlo Ltd. 74,767 no. defective consumer meters replaced out of 76,378 no. in scope. March,2021
Village Infrastructure for access to power for all Rural HH. 1,244 km renovation of LT line by AB Cable completed out of 1,307 km in scope.
376 no New Distribution Transformer installed out of 390 no. in scope. 42 no. augmentation of DTR completed out of 42 no. in scope.
14 Darjeeling Metering Departmental Execution 24,154 no. defective consumer meters replaced out of 26,492 no. in scope. March,2021
Village Infrastructure for access to power for all Rural HH. 570 km renovation of LT line by AB Cable completed out of 570 km in scope.
268 no New Distribution Transformer installed out of 310 no. in scope.
Sansard Adarsh Gram Yojona (SAGY) Departmental Execution Work completed. --
15 Jaipaiguri(including Alipurduar) Feeder Segregation LOA issued M/S L&T Ltd. 04 no Feeders are commissioned out of 06 no. feeders. March,2021
Metering 1,33,322 no. defective consumer meters replaced out of 1,37,790 no. in scope.
Village Infrastructure for access to power for all Rural HH. 1,267 km renovation of LT line by AB Cable completed out of 1,267 km in scope.
488 no New Distribution Transformer installed out of 557 no. in scope.
16 Coochbehar Feeder Segregation LOA issued M/S L&T Ltd 04 no Feeders are commissioned out of 04 no. feeders. March,2021
Metering 1,16,015 no. defective consumer meters replaced out of 1,16,015 no. in scope.
Village Infrastructure for access to power for all Rural HH. 1,081 km renovation of LT line by AB Cable completed out of 1,081 km in scope.
458 no New Distribution Transformer installed out of 461 no. in scope.
Electrification of Habitations less than 100 HH. M/S BISPA India Ltd Work Completed. --
17 Uttar Dinajpur Feeder Segregation LOA issued M/S L&T Ltd. 10 no Feeders are commissioned out of 16 no. feeders. March,2021
Metering 98,178 no. defective consumer meters replaced out of 1,08,243 no. in scope.
Village Infrastructure for access to power for all Rural HH. 807 km renovation of LT line by AB Cable completed out of 812 km in scope.
522 no New Distribution Transformer installed out of 642 no. in scope.
18 Dakhin Dinajpur Feeder Segregation LOA issued M/S L&T Ltd. 16 no Feeders are commissioned out of 18 no. feeders. March,2021
Metering 92,775 no. defective consumer meters replaced out of 96,275 no. in scope.
Village Infrastructure for access to power for all Rural HH. 904 km renovation of LT line by AB Cable completed out of 908 km in scope.
477 no New Distribution Transformer installed out of 527 no. in scope. 404 no. augmentation of DTR completed out of 484 no. in scope.
B . Status of New 33/11 KV Substation Under System Strengthening in DDUGJY Scheme As on 31.01.2021
SL NO: District
Departmental
Turnkey Execution
Number Status of work Target for completion Number Status of Work Name of Turnkey agency Target for completion
1 North 24 parganas 3 All Sub-Stations commissioned. --
-
2 South 24 parganas and Biddhannagar 4 All Sub-Stations commissioned. --
3 Howrah 4 All Sub-Stations commissioned. --
4 Burdwan 10 All substations comissioned. --
5 Hooghly 3 All Substation Comissioned. --
6 Birbhum 3 All Sub-Stations commissioned. -- 2 All Sub-stations Comissioned. M/S Bajaj Electricals Ltd --
7 Malda 5 All Sub-stations Comissioned -- 3 All Sub-stations Comissioned M/S Bajaj Electricals Ltd --
8 Murshidabad 4 All Sub-Stations commissioned. -- --
9 Nadia 4 3 No Substation Comissioned. --
10 Purulia 1 Sub-Stn Commissioned --
11 Paschim Midnapur 6 All Sub-Stations Comissioned. --
12 Purba Midnapur 4 All Sub-Stations commissioned. --
13 Bankura 0 -- -- 3 All Substations Comissioned. M/S Bajaj Electricals Ltd --
14 Darjeeling 2 1 No Substation Comissioned. February,2021 : 1 No 2 All Substations Commissioned M/S Bajaj Electricals Ltd --
1 No Works is under progress
15 Jaipaiguri (including Alipurduar) 1 Sub-Stn Commissioned -- 4 All Substations Comissioned. M/S Bajaj Electricals Ltd --
All Substations Comissioned. M/S T&T Ltd --
16 Coochbehar 5 4 No Substation Comissioned. March,2021 : 1 No --
1 No Works are under progress
17 Uttar Dinajpur 4 All Sub-Stations commissioned. --
18 Dakhin Dinajpur 1 Sub-Stn Commissioned -- 2 All Substations Comissioned. M/S T&T Ltd --
C . Status of Augmentation of Existing 33/11 KV Substation in DDUGJY Scheme as on 31.01.2021

SL NO: Name of the District Departmental Execution
Scope of PTR Augmented (No) Status of work Target for completion
1 North 24 parganas 7 7 -
2 South 24 parganas and Biddhannagar 11 9 March, 2021
3 Howrah 8 8 -
4 Burdwan 11 9 March, 2021
5 Hooghly 5 5 --
6 Birbhum 10 8 March, 2021
7 Malda 5 5 -
8 Murshidabad 13 12 March, 2021
9 Nadia 9 9 -
10 Purulia 0 0 -
11 Paschim Midnapur 10 9 March, 2021
12 Purba Midnapur 12 10 March, 2021
13 Bankura 14 14 --
14 Darjeeling 7 7 -
15 Jaipaiguri
(including Alipurduar)
7 6 March, 2021
16 Coochbehar 6 6 -
17 Uttar Dinajpur 8 8 -
18 Dakhin Dinajpur 3 3 -